  1. 1.0 Call to Order and Pledge of Allegiance
  2. 2.0 Roll Call
  3. 3.0 Public Participation
  4. 4.0 Approval of Minutes approved Pass
  5. 5.0 Unfinished Business
  6. 6.0 New Business
  7. 7 An Ordinance Amending Title IX, Chapter 99, of the Lombard Village Code in regard to Trees and Shrubs A recommendation of the Public Works and Environmental Concerns Committee to amend Title IX, Chapter 99, of the Lombard Village Code in regard to Trees and Shrubs. Staff proposes an increased fee for tree planting and a more thorough explanation of the Ordinance. (DISTRICTS - ALL) 250360 discussed Pass
  8. 8 Coarse Aggregate Material Purchase, Change Order No. 1 Reflecting an increase to the contract with Vulcan Materials in the amount of $30,000.00. This Change Order is for increased quantities needed to make repairs. (DISTRICTS - ALL) 250372 approved Pass
  9. 9 FY2025 Manhole Rehabilitation Change Order No. 2 Reflecting an increase to the contract with Kim Construction Company, Inc. in the amount of $71,738.82. This Change Order adds forty six manholes to the contract. The additional repair work was generated from manhole inspections performed under the 2025 sewer televising contract. (DISTRICTS - ALL) 250375 approved Pass
  10. 10 641 N. Main Street Drainage Basin Project, Final Balancing Change Order No. 2 Reflecting an increase to the contract with Lima Contractors, Inc. in the amount of $133,214.99. This Change Order includes the increased quantity of non-special waste and adjusts pay item quantities for all construction categories. (DISTRICT #4) 250378 approved Pass
  11. 11 Highland Avenue Sewer Separation, Final Balancing Change Order No. 2 Reflecting an increase to the contract with John Neri Construction Company in the amount of $82,210.30. This Change Order includes field-measured quantities of existing pay items, two new authorized unit prices items and two force amounts. Changes were primarily related to poor soils both on South Chase Avenue and Division Street and a water main break during roadway reconstruction. (DISTRICT #5) 250383 approved Pass
  12. 12 FY2025 Sidewalk and Curb Improvement Program, Final Balancing Change Order No. 1 Reflecting a decrease to the contract with Globe Construction, Inc. in the amount of -$12,999.64. This Change Order is intended to adjust the contract quantities. (DISTRICTS - ALL) 250385 approved Pass