Request approval of a change order of less than 10% - Public Works Department, 21RFP130845K-BKJ, Progressive Design-Build Services for Atlanta Newnan Road Pump Station and Force Main in an amount not to exceed $800,000.00 with Reeves Young/GMC, JV (Atlanta, GA) to cover conflicts of rock excavation/removal and to extend the contract final completion date by 180 calendar days to June 3, 2024. Effective upon BOC approval. (APPROVED UPON ADOPTION OF THE CONSENT AGENDA) ..body

Consent - Health and Human Services Agenda Ready Introduced August 29, 2023

What this record is

Amount
$800K
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Board of Commissioners
Requested by
Public Works
Introduced
August 29, 2023
On agenda
December 6, 2023