docketcity.com
23-0075

Request approval of a change order less than 10% - Public Works, 17RFP031617K-DJ Progressive Design/Build Services for Big Creek Water Reclamation Facility (WRF) Expansion Project Phase 2B in an amount not to exceed $339,444.13 with Archer Western-Brown and Caldwell Joint Venture (JV) (Atlanta, GA) to cover costs associated with eight (8) inclement weather days and additional material (electrical wiring) to connect the new facility to the Georgia Power Substation. Effective upon BOC approval. (APPROVED UPON ADOPTION OF THE CONSENT AGENDA)

Consent - Health and Human Services Agenda Ready Introduced November 1, 2022

What this record is

Amount
$339K
Runs until
no end date published in this record
Type
amendment
Field
Utilities & energy

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Board of Commissioners
Requested by
Public Works
Introduced
November 1, 2022
On agenda
February 1, 2023