Request approval of a change order less than 10% - Department of Real Estate and Asset Management, 21RFP22421K-DB, Construction Management at Risk Services for the New Fulton County Animal Shelter Facility in the total amount of $2,823,544.00 with Winter Johnson Group (Atlanta, GA), a joint venture comprised of The Winter Construction Company and Johnson Construction Services, to modify existing contract for additional funding due to substantial costs attributable to price escalation for equipment, materials and supplies, scope changes required by regulatory agencies during permitting processes, and unforeseen conditions of developing a raw site for the new construction project for the Fulton County Animal Shelter Facility (FCAS). Effective upon BOC approval. (APPROVED) ITEM REMOVED FROM THE CONSENT AGENDA FOR SEPARATE CONSIDERATION AS REQUESTED BY COMMISSIONER ELLIS

Consent - Open & Responsible Government Passed Introduced October 19, 2022

What this record is

Held by
Winter Construction Company 2 records across this site
Amount
$2.82M
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Winter Construction Company also holds

Request approval of a change order less than 10% - Department of Real Estate and Asset Management, 21RFP22421K-DB, Construction Management at Risk Ser… $187K Fulton County, GA
Committee
Board of Commissioners
Requested by
Real Estate and Asset Management
Introduced
October 19, 2022
On agenda
November 16, 2022
Passed
November 16, 2022