docketcity.com
22-0541

Request approval of Guaranteed Maximum Price (GMP) - Department Public Works, 21RFP130845K-BKJ, Progressive Design-Build Services for Atlanta Newnan Road Pump Station and Force Main in an amount not to exceed $18,519,592.88 with Reeves Young /GMC JV (Atlanta, GA), to perform all construction activities associated with the installation of two new pump stations and associated force main pipelines to serve the South Fulton County area. Effective upon issuance of the Notice to Proceed (NTP) with work to be completed within 15 months of the issuance of NTP. (APPROVED)

CM Action Item - Health and Human Services Passed Introduced June 27, 2022
Committee
Board of Commissioners
Requested by
Public Works
Introduced
June 27, 2022
On agenda
August 3, 2022
Passed
August 3, 2022