#R6954
Temp. Reso. #R6954 approving Amendment No. 1 to Agreement with H.G. Construction, Development & Investment, Inc., for Miramar Parkway Streetscape from SW 68 Avenue to SW 64 Avenue, to revise the contractor bid calculation error from the not-to-exceed amount of $1,490,300 to $1,500,300; authorizing the City Manager to execute the Amendment No. 1 to reflect the revised not-to-exceed amount of $1,500,300, and allocating a Construction Contingency Allowance of $250,000, for a total project cost not-to-exceed $1,750,300. (City Engineer Bissy Vempala and Procurement Director Alicia Ayum)
What this record is
- Amount
- $1.75M
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- CITY COMMISSION REGULAR MEETING
- Requested by
- Engineering Services
- Introduced
- April 17, 2019
- On agenda
- June 12, 2019
- Passed
- December 31, 2023