22-0066
Receive an update on Phase II of the Civic Center Complex Project, approve a Consultant Contract Amendment with Darden Architects for an amount not to exceed $1,356,500 and authorize the appropriation of $1,500,000 from the Civic Center Reserve Fund.
What this record is
- Held by
- Darden Architects 3 records across this site
- Amount
- $1.36M
- Runs until
- no end date published in this record
- Type
- amendment
Read automatically from the title of the official record. The source document below is authoritative.
Darden Architects also holds
Approve a Consultant Contract Amendment with Darden Architects for the Civic Center Phase 2 project for an amount not to exceed $1,147,748, and author… Authorize the City Manager to execute a contract with the architecture firm of Darden Architects, Inc. for Architectural/Engineering services for the …- Committee
- Visalia City Council
- Introduced
- February 7, 2022
- On agenda
- April 4, 2022
- Passed
- April 4, 2022