docketcity.com
23-326

CONSIDER ADOPTING RESOLUTION INCREASING THE TOTAL AUTHORIZATION FOR THE CONTRACT WITH GHILLOTI BROTHERS, INC. FOR CONSTRUCTION OF THE RUMRILL BOULEVARD COMPLETE STREETS PROJECT BY $2,426,397, FOR A TOTAL AUTHORIZATION NOT TO EXCEED $19,550,800. CEQA: The Rumrill Boulevard Complete Streets Project is categorically exempt under the California Environmental Quality Act (CEQA), Section 15301, Existing Facilities (Class 1) of the CEQA Regulations. Moreover, since the project is also receiving federal funding, the project was also determined to be categorically exempt under the National Environmental Policy Act (NEPA), Section 23 CFR 771.117 (c)(3).

RESOLUTION Consent Calendar Introduced July 27, 2023

What this record is

Amount
$19.6M
Runs until
no end date published in this record
Type
contract
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
City Council
Introduced
July 27, 2023
On agenda
August 7, 2023