23-0351
Change Order Report: Change Order #1 with CMH Construction, LLC for the Park Shelter Structural Repairs Project in the amount of $20,445.58.
What this record is
- Held by
- CMH Construction, LLC 2 records across this site
- Amount
- $20K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
CMH Construction, LLC also holds
Approval of Contract with CMH Construction, LLC for Park Shelter Structural Repairs in the Amount of $142,428.00- Committee
- City Council
- Requested by
- Capital Facilities
- Introduced
- June 28, 2023
- On agenda
- July 5, 2023
- Passed
- July 5, 2023