20-0426
Change Order Report: Change Order #2 with Cornerstone General Contracting Inc. for Providence Valdez Medical Center Copper Pipe Replacement in the Amount of $17,581
What this record is
- Held by
- Cornerstone General Contracting Inc 3 records across this site
- Amount
- $18K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Health & social
Read automatically from the title of the official record. The source document below is authoritative.
Cornerstone General Contracting Inc also holds
Approval of Change Order with Cornerstone General Contracting, Inc. for Providence Valdez Medical Center Copper Pipe Replacement in the Amount of $43,… Change Order Report: Contract Amendment with Cornerstone General Contracting, Inc. for the Providence Valdez Medical Center Copper Pipe Replacement.- Committee
- City Council
- Requested by
- Capital Facilities
- Introduced
- August 28, 2020
- On agenda
- September 15, 2020
- Passed
- September 15, 2020