docketcity.com
20-0424

Change Order Report: Change Order #4 with Harris Sand & Gravel Inc. for Pavement Management Phase I - West Egan Drive in the Amount of $25,500

Report Filed Introduced August 28, 2020

What this record is

Held by
Harris Sand & Gravel Inc 24 records across this site
Amount
$26K
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Harris Sand & Gravel Inc also holds

Change Order Report: Change Order with Harris Sand & Gravel for the Valdez SBH H-K Major Reconstruction project in the amount of $28,496.01 $28K Valdez, AK Procurement Report: Service Agreement with Harris Sand & Gravel, Inc. (2025 Asphalt & Sidewalk Repair) in the Amount of $60,477.00 $60K Valdez, AK Approval of Change Order #1 with Harris Sand & Gravel for Pavement Management Phase IIIB Pioneer Drive in the Amount of $104,650. $105K Valdez, AK Approval of Contract with Harris Sand & Gravel Inc. for Pavement Management Phase III-B Pioneer Drive in the Amount of $2,586,057.50 $2.59M Valdez, AK Procurement Report: Contract with Harris Sand & Gravel for Shoup Street Drainage and Asphalt Improvement Project in the Amount of $46,000.00 $46K Valdez, AK

All 24 records for Harris Sand & Gravel Inc →

Committee
City Council
Requested by
Capital Facilities
Introduced
August 28, 2020
On agenda
September 15, 2020
Passed
September 15, 2020